Dubai Metro, United Arab Emirates
|
Construction delays
Work officially commenced on the construction of the metro on March 21, 2006. In February 2009, a top RTA Rail Agency official said the $ 4.2 billion Dubai Metro project would be completed on schedule despite global crisis. However only 10 out of 29 metro stations of the red line opened on 9 September 2009.
Construction of the 18 stations on the red line and another 18 on the green line restarted on 7 February 2010, according to contractors, after a settlement was reached with a Japanese-led consortium over disputed payments of about $ 2 billion-$ 3 billion. Construction of all 29 metro stations on the red line was declared complete on April 28, 2010 by the acting chief of the RTA Rail Agency.
|
|